Here are some pictures from the move showing our old and new Data Center, our servers, and some of our sysadmins.
All in all the process involved around 2 weeks of planning, 10 people, 3 cars, a few hundred feet of cable, 10 hours of deracking, driving, and installing, and a week cleaning up afterwards.
It’s good to know that Perdita, Pongo, Patch, Penny, Pepper, Taishi, Rambo, Takara, Tinkerbell, Chernushka, Strelka, Bars, Pink, Oscar, Fenris, Greyhound, Odie, Marmaduke, and Sirius are all running smoothly in their new pound!
- Some didn’t sleep too much the previous night
- Things were a bit complicated at the old data center.
- Pre-move preparations: Kim makes sure the server has enough memory.
- Starting to derack…
- On a roll again: Out from under.
- Coordinations
- Arriving at the new Data Center
- So far so good!
- Unpacking
- Unloading in the basement after 6 security doors
- Full power and network redundancy, and top notch fire prevention systems.
- Installing in the new, shiny racks in the new Data Center.
- This way?
- Easy does it…
- That’s the one
- Cabling…
- More cabling…
- That should be it… Right colors and all!
- On the console.
- Sigurd starts taking services up.
- Load balancers, MX servers, app servers, storage units, database servers, and a few more all done.
- *tweet*
- The last plug
- All systems are go!
- All is good in Runbox land :)